Woods of Fairview project information

Feed RSS: Subscribe to Woods of Fairview project feed
(Learn about RSS feeds and other ways to receive updates)

Updated information on Woods of Fairview

Construction management plan (PDF)


Update: November 22, 2013

Utility installation has been completed. Road paving will begin the week of November 25.


Planning Project
Updated

November 22, 2013

Project number

13001.13a

4415 Fairview Ave

Location map for Woods of Fairview project, located at 4415 Fairview Ave.

Project description

The applicant is proposing to rezone 4415 Fairview Ave. from R-1 to PUD and subdivide the 3.2 acre site into 7 lots that would range from 13,878 square feet to 21,275 square feet in size.

Meetings
Introduction of Ordinance Date: March 4, 2013
Action: Introduced ordinance and referred to the planning commission.
View meeting details
Tentative Public Hearing Date: April 25, 2013
Action: Recommended the city council approve the project.
View meeting details
Meeting Date: May 13, 2013
Action: Tabled to June 3, 2013.
View meeting details
Meeting Date: June 24, 2013
Action: Approved the project.
View meeting details
Meeting Date: September 30, 2013
Action: Approved the project.
View meeting details
Comments/questions
Plans

Narrative and plans (PDF: 3 MB)

Revised plans: April 2, 2013 (PDF: 15 MB)

Revised plans: June 4, 2013 (PDF: 16 MB)

Construction management plan (PDF)

Reports

Staff report for city council meeting: March 4, 2013 (PDF: 3 MB)

Staff report for planning commission meeting: April 25, 2013 (PDF: 8 MB)

Staff report for city council meeting: May 13, 2013 (PDF: 8 MB)

Staff report for city council meeting: June 24, 2013 (PDF: 10 MB)

Staff report for city council meeting: September 30, 2013 (PDF: 3 MB)

Updates

Update: November 22, 2013

Utility installation has been completed. Road paving will begin the week of November 25.


Update: October 29, 2013

The grading permit for the Woods of Fairview project was issued on October 21. Over the next several weeks expect to see the following:

  • Demolition of existing structures.
  • Tree removal.
  • Site grading.
  • Installation of utilities.
  • Street construction.

Update: March 22, 2013

The applicant is revising proposed grading and stormwater plans. Updated plans will be posted to this page when they are received. A planning commission hearing date will not be set until the updated plans have been submitted and reviewed by city staff.