St. Alban’s Woods project information

Feed RSS: Subscribe to St. Alban’s Woods project feed
(Learn about RSS feeds and other ways to receive updates)

Updated information on St. Alban’s Woods

Construction management plan (PDF: 1 MB)


Update: November 22, 2013

On November 21, a building permit application was submitted for the first new home in the subdivision. The home will be constructed on the southernmost lot along Lilac Lane.


Planning Project
Updated

November 22, 2013

Project number

12042.12a

3516 Rainbow Dr.

Location map for St. Alban’s Woods project, located at 3516 Rainbow Dr..

Project description

St. Albans Land, LLC is proposing to divide the existing property at 3516 Rainbow Drive into seven, single-family residential lots. Four of the lots would be accessed via Lilac Lane and three of the lots would be accessed via Rainbow Drive. The existing home would be moved to one of the newly created lots.

Meetings
Introduction Date: January 7, 2013
Action: Introduced the ordinance and referred it to the planning commission.
View meeting details
Public Hearing Date: January 17, 2013
Action: Planning Commission approved January 17, 2013.
View meeting details
Meeting Date: January 28, 2013
Action: Continued to a date no later than March 4, 2013.
View meeting details
Meeting Date: March 4, 2013
Action: Directed preparation of plan to be presented to council on March 25.
View meeting details
Meeting Date: March 25, 2013
Action: Approved the project.
View meeting details
Comments/questions
Plans

Narrative and plans (PDF: 4 MB)

Revised plans: preliminary plat (PDF: 1 MB)

Revised plans: landscape (PDF: 1 MB)

Revised plans: grading (PDF: 1 MB)

Construction management plan (PDF: 1 MB)

Reports

Staff report for city council meeting: January 28, 2013 (PDF: 10 MB)

Staff report for city council meeting: January 7, 2013 (PDF: 4 MB)

Staff report for planning commission meeting: January 17, 2013 (PDF: 9 MB)

Staff report for city council meeting: March 4, 2013 (PDF: 11 MB)

Staff report for city council meeting: March 25, 2013 (PDF: 11 MB)

Updates

Update: November 22, 2013

On November 21, a building permit application was submitted for the first new home in the subdivision. The home will be constructed on the southernmost lot along Lilac Lane.


Update: July 25, 2013

The contractor has completed paving the private drive.


Update: July 22, 2013

The contractor has begun construction of the private drive. The contractor has tentatively scheduled paving of the private drive and patching of Rainbow Drive to begin next week.


Update: July 11, 2013

The contractor has begun construction of the private drive. The contractor has tentatively scheduled paving of the private drive and patching of Rainbow Drive to be completed in late July.


Update: July 3, 2013

The contractor has tentatively scheduled construction of the private drive to begin next week.


Update: June 28, 2013

The contractor has completed sanitary sewer and water main line and service installation. The contractor has tentatively scheduled construction of the private drive to begin next week.


Update: June 20, 2013

The contractor has completed tree removal. The contractor has begun sanitary sewer and water main installation. The contractor will need to shut down the water main to connect the new line. Temporary service interruptions will be coordinated with those affected.


Update: June 13, 2013

The contractor has begun tree removal on the site. The contractor has tentatively scheduled sanitary sewer and water main installation to begin next week.


Update: June 12, 2013

A grading permit will be issued the week of June 10. The permit was reviewed and approved by planning, engineering, and natural resources city staff. The on-site activity covered by the permit includes: installation of public utilities, removal and reconstruction of the private driveway off of Rainbow Drive, and associated tree removal.